Environmental groups are calling for City Water, Light & Power, the city’s publicly-owned utility company, to allow more public involvement in the development of its energy planning and forecasting as their concerns about lack of commitment to a clean energy transition grow stronger.
CWLP is in the process of selecting a vendor to spearhead the utility’s development of an Integrated Resource Plan (IRP), which is an analysis of available power sources and outlook for future demands over a 20-year time period. It also includes a five-year action plan.
Under the Clean and Reliable Grid Affordability Act (CGRA) that went into effect this year, CWLP must begin its IRP process in 2027 and submit an updated report every five years.
CWLP produced its first IRP in 2020 and held eight public meetings where residents were able to review the completed report and provide comments and questions.
Under CGRA, CWLP would only be required to hold two public meetings, said Lori McKiernan, a member of the Coalition for Springfield’s Utility Future. In addition to calling for CWLP to increase the number of public meetings, the coalition wants public engagement early on in the process.
McKiernan said the challenge with the traditional public meeting format is “the public doesn’t have any chance to read through the documentation and prepare intelligent questions.”
She said public engagement introduced early in the development of the IRP helps to broaden the scope beyond what CWLP sets forth.
“An IRP should not just be an engineering report,” McKiernan said. “It shouldn’t just say ‘Gas costs this much, renewables cost this much and then give their recommendation on what the best solution is. The IRP process should include community goals, benefits to the community and public health inputs, and how our jobs are going to be affected by it.”
According to McKiernan, the vendor CWLP chooses to develop the IRP is not likely to be local and to have this kind of information or insight.
“So, we want the public to be able to contribute towards those ideas to get a really strong IRP process,” she said.
The coalition also wants CWLP to incorporate milestones for meeting zero-carbon emissions by 2045 as laid out by the Climate and Equitable Jobs Act (CEJA), signed into law by Gov. JB Pritzker in 2021.
“That’s the law,” McKiernan said. “So they need to create a plan that starts working toward that, based on the recommendations that the IRP report gives them.”
McKiernan said so far CWLP has been unwilling to define a clean energy goal, and it’s come at a cost with the denial of a Small Utility Clean Energy Planning grant for $200,000 toward planning and purchases in line with meeting the CEJA’s stated goal. The funds are administered through the Illinois Finance Authority with federal dollars provided under the 2024 Inflation Reduction Act.
“They would not state within that grant that they were going to transition to clean energy. So, it was just so poorly written,” she said.
McKiernan said the Coalition for Springfield’s Energy Future offered to help rewrite the grant application, but were told CWLP has chosen not to refile.
Illinois Times requested an interview with CWLP leadership and instead received a written response from CWLP spokesperson Amber Sabin on Nov. 20.
“We’ve met with the Coalition a few times over the last year or two on this topic and most recently this summer, where we specifically discussed our upcoming request for proposal for the Integrated Resource Plan,” Sabin wrote. “We have robust public engagement planned and that was included in the scope that went out in the RFP.”
Regarding the state grant that CWLP was denied, Sabin said the grant “would limit the scope of the IRP and options to study if forced to follow CEJA goals rather than the CEJA requirements.”
She referenced the state’s own IRP that was released on Nov. 16, which recommends less robust measures toward achieving carbon-free emissions as the demand for energy due to data centers grows.
According to a joint press release from Illinois Commerce Commission, the Illinois Power Agency and the Illinois Environmental Protection Agency, their reports recommend “extending closure deadlines from gas and oil units – not from coal units.”
The agency still calls for meeting the closure deadline for coal-fueled power because they “produce more pollution.”
Even so, Sabin writes, “The state of Illinois, in its IRP that just came out this week, also isn’t following CEJA goals, just the requirements. In addition, these are requirements they are now considering changing…,” she wrote.
Illinois Times interviewed Scott Rogers, CWLP’s chief engineer, in August about the utility’s sense of urgency to meet the 2045 deadline for carbon-free energy.
“So, we would not take any action on something that’s now projected 20 years out, because technology is going to change, legislation is going to change,” he said. “When you change governors in the state of Illinois or you change the presidency, you don’t know their mandates or what their ideas are on the energy side and being carbon neutral or not.”
Rogers said he’s agnostic as to the energy source the city relies on, “as long as it’s cheap, reliable and affordable.”